Unit 2 from Cernavoda, decoupled from the energy system
Unit 2 CNE Cernavoda will enter the planned stop program starting May 11 and the discrimination from the National Energy System will take place at 11:00, SN Nuclearelectrica announced on Friday.
‘The planned stops represent complex projects, initiated 24 months before the planned date, having a project management team, graphic graph, human resources planning and appropriate budgeting. During the planned stop, activities from the following programs will be carried out: the preventive maintenance program; The corrective maintenance program; Inspection program; The compulsory test program during the planned stops; The project implementation program ‘, it is stated in the Nuclearelectrica announcement transmitted to the Bucharest Stock Exchange.
The works will be carried out in safe conditions for the staff of the central, public and the environment, according to the approved procedures used in Cernavoda CNE, the source said.
Nuclearelectrica has as fields of activity the production of electric, thermal and nuclear fuel. The company operates under the authority of the Ministry of Energy, the Romanian state holding 82.49% of the shares, and other shareholders 17.50%, after the listing of the stock company in 2013.
The Nuclear Power Plant (CNE) The Cernavoda branch exploits two Candu nuclear units, which are two of the most efficient units of the more than 400 nuclear power plants, a nuclear fuel factory and is in progress of an integrated fuel cycle by purchasing an uranium concentration processing, to support the long -term investment projects.