Home » « Too many parallel problems for the project we need to hand over the world for a year and a half »: do you delete works on Expo? – Economy

« Too many parallel problems for the project we need to hand over the world for a year and a half »: do you delete works on Expo? – Economy

« Too many parallel problems for the project we need to hand over the world for a year and a half »: do you delete works on Expo? – Economy


In about two years, Serbia expects an exposition exhibition, and according to the statements of officials, in a multimesic delay. In addition, the realization of the budget for these Casca projects, so the question opens whether the work will be completed in time with this dynamic.

The exhibition will last for three months, and should receive between three and four million visitors, according to the evaluation of officials. The state for himself Expo It allocates about 1.2 billion euros, while for the entire project around the Exp and all accompanying works, it should be opted for 18 billion.

In this year’s budget, slightly more than 393 million euros is allocated for the expo, and additional for the national stadium is another 18.6 million.

However, budget execution In the first four months this year, it is very low when these projects are viewed.

As it has previously written today, for financing facilities within the Expo until the end of April, only 0.54 percent of total funds were paid. When it comes to the National Stadium, the situation is even worse, because only 0.16 percent of the total planned funds is funded.

These numbers do not encourage, especially when they look together with statements of officials on physical delay in these projects.

Serbian President Aleksandar Vučić recently stated that the construction of the national stadium is as many as four months late, and it is planned to be open right on it.

« We can compensate for two months through working in three shifts and now we look at where to compensate for another two months, because we have scheduled that the great opening is at the largest and most beautiful stadium, » Vučić said.

And Minister of Finance Siniša Mali, at the meeting with the ambassador of China, said the works would have to intensify.

« Business has a lot, the state of Serbia pays on time and that is why we expect everything to be done on time. There is no time to delay with the performance of works, » said Mali.

Marko Milanović from the Fiscal Council explains that it is strange that the total realization is less than we would expect, but it is too early for solid conclusions that at the level of the total state investment will be less than the plan.

« It is common to have unpredictable monthly or quarterly dynamics. In one day it can be ‘compensated’ to see strictly watching data. It still does not claim that it will be at the year level, » he said.

Some projects turn out, and the second break plan, our interlocutor is added.

« When looking at the mass, nominal size and share in GDPs are practically shaken with the plan. Although it is more slowly than the plan or expectations, but it will not be strange to the end of the year, » MiLanović indicates.

He reminds that similar happened last year.

« Last year last year, realization was also slower, less than the plan and was eventually pierced the plan for the national stadium and for the expo, it was practically doubled, » said Milanovic. « Says Milanovic. »

Source: Ministry of Finance Illustration: Chatgpt

It clarifies and does not always have to be financial implementation to follow that physical.

« So if some problems in realization exist, I have been financially financially. They have long provided finances for it, but that the state has no money for that, it does not stand, » Milanovic concludes.

On the other hand, an authorized real estate assessor Nikola Seneshi believes that the delay of works on the Expo complex is not technically, but a fiscal problem.

He believes that extremely low budgetary benefits for capital projects in the first four months clearly indicate the absence of the planned financing dynamics.

« At the same time, it is increasingly evident that a significant part of public money is reduced to the social stability before possible elections. In itself, it is not so large investment, but are many others who are currently related to it, » Warning Senesi. « 

He adds that Serbia has a budget reserve and that these funds are currently being actively been spent, but not to expo, neither of the development projects, but predominantly on short-term fiscal needs that do not have long-term development effect.

« According to my knowledge, significant delays recorded other key segments of expo infrastructure, while the tempo of the construction of the Belgrade – Niš, which would allow the airport » Konstantin Veliki « in the expo, there is no speech in that dynamic, » Senemi points out.

Also, according to him, more hotels that received funds from the funds of the Serbian Development Agency (Ras) with realization, which endangers the capacities necessary for receiving visitors and delegations.

However, as it says, according to what can be seen in the field, a residential settlement within the Expo project progresses relatively stable.

« However, in space where the halls should be raised, and early structural procedures, foundation and preparation of terrain should continue, which clearly shows that key objects are not even close to the final phase, » he states.

Seneshi emphasizes that a serious problem and slowing down the dynamics of payment between the state, the Chinese artist and domestic subcontractors, especially small and medium-sized firms.

« Contractual obligations are made with a delay, which directly affects their further sustainability on this project. The small subcontractors, which make the spine of operational implementation, may not be able to endure that further risky dynamics of the project », claims.

As an additional obstacle, according to him, the latest withdrawal of the law known as « Lex Specialis » from the parliamentary procedure should be given.

« This law should have accelerated the process of issuing a use permit for key objects within the Expo, but its disposal leaves open legal issues and risks around the timely formal object transfection », explains Seneches.

Our interlocutor is afraid that, due to all the above, the politicization of the whole problem could occur.

« And through an attempt to transfer responsibility to political opponents, instead of recognized project management, but at this point, I seem to be too parallel for one project we need to hand over the world for a year and a half, » Seneches concludes.

Civil engineer Danijel Dašić for today says that the Chinese looked very seriously that partnership in potentially corrupt affairs with the Republic of Serbia, does not benefit them.

« The fall of the canopy in Novi Sad echoed widely and widely. Numerous documents that indicate potential corruption and money laundering in this project, and a very important role, and complaints of Chinese partners, » he states.

Dašić believes that one of the problems is also in the absence of quality planning documents.

« The authority attempted to legalize the construction and use of expo without a use permit. It is absolutely cannot be completed in time, and that this process is in accordance with the Law on Planning and Construction, and it has become clear to everyone in the authorities, » he warns him.

The construction of quality infrastructure facilities, as it claims, was never the goal of this government.

« The goal is ‘installation’, which is most importantly efficiently, and with as few controls, without all the necessary licenses, because the authority requires a proven media wall in the birdhop, over sabotage and ‘burned’ fuse in The newly built covid hospital, all the way to the ‘explosives’ by which « some’ crashed the canopy, all this passes on an empty mind, as a bad sandwich on an empty stomach, » warns Dasic.