I

The company denies that he is doing unauthorized work in Liptovska Mara.

Liptovský Mikuláš. On the banks of Liptovska Mara, in the premises of the local gravel mining area, the concrete plant is growing. The building office, which has a decisive word, did not allow it.

The editorial office came to us that clearly document that the operation has been added to the unmistakable mobile device for the production of concrete. It also includes three forces that already stand. It belongs to RBR concrete, which operates several concrete in Slovakia, the nearest one in Ružomberok.

The company denies that he is doing work for which a building permit is needed. This is a place that is adjacent to the upcoming city beach in Liptovska Mara. So people will be recreated in the neighborhood of the concrete plant, which is a moderate source of pollution. They will also use the same and only access road.

Can produce more times than reported to the authorities

We turned to the Ministry of the Interior, under which the district offices commencing on similar intentions. Their opinion shows that the Liptovsky Mikulas District Office gave several opinions to the concrete plant.

However, it is a statement that the petitioner, RBR concrete, needs to prove the application for a zoning decision and the subsequent building permit. These can only be issued by the Liptovsky Mikulas building office.

From the documentation provided by the Ministry of the Interior, we learned that this is a mobile concrete concrete type SBM Euromix 3300 SM. The manufacturer presents this type on its website as a concrete room that can produce up to 145 cubic concrete in an hour.

However, in the statement of the Liptovsky Mikulas District Office, RBR declares that he wants to produce at most 10.6 cubic meters per hour in Liptovska Mara.

Related article The modernization of the railway under the Tatras is returning ten years back, the ministry has reservations about it Read

« Part of the old gravel sorting technology will be destroyed and a mobile concrete is placed on the proposed paved pebble surfaces, which will be connected to electricity from the existing switchgear and water from the sorting line.

The District Office issued consent to the location of the medium -source construction of the air pollution last September, notifying that it does not replace the decision to place the construction under the Building Act, which must be requested by the competent authority. This is the Liptovsky Mikulas building office.

Tightly suited the limits for the EIA

According to the project submitted, the mobile concrete is used in one -shift operation with an eight -hour working time. Plan to work 200 days a year. This means that with an hour of 10.6 cubic meters per hour they produce 49,200 tons of concrete per hour.

The one -year -old planned production is an important indicator. If it were more than 50,000 tons per year, RBR concrete would have to submit the intention to assess the environmental impact assessment, to go through the process of the so-called small EIA, as it would be subject to detection procedure. For example, the public or civic associations could already participate in it.

It is a common practice that the petitioners use quite often not only in the construction industry. For example, if the shopping center or the new accommodation had more than one hundred parking spaces, it would also be subject to the investigation. Therefore, it is often the case that developers propose buildings with 99 parking spaces to close the EIA process.

The building office has no documentation

The concrete plant on the shore of Liptovska Mara near the railway line to be translated, ie the Liptovsky Mikulas, the building office did not allow.



Related article Railway megaproject in Liptov. They wrote a tender for the reloading of the track near Liptovský Mikuláš Read

« We only know that on Friday, March 21, an application for a building office for the concrete plant was submitted electronically. In the coming days, it will be consulted by the investor’s representative with the project documentation in printed form and opinions of the bodies concerned, » said Katarína Šuveríková, head of the Liptovsky Mikulas building office. The extent of the builder’s request.

This is a territory reserved for surface mining

If, on the basis of the project, the building office assesses that it is a construction, it will also need a binding opinion of the department of the main architect Liptovský Mikuláš.

The land -use plan says that the shore of Liptovska Mary in Palúdzka is a mixed area with the predominance of facilities for Sport and recreation. At the same time, part of it defines as a conquest space of gravel, there are the same rules there as for the reserved area of ​​surface mining.

However, mining is not the territory of construction production, the Liptovsky Mikulas Territorial Plan defines separately. It will therefore be up to the assessment of the Liptovsky Mikulas formation of the chief architect, whether the production of concrete in Liptovska Mara is or not in accordance with the zoning plan.