Columns have been formed on the Lart from Bratislava for weeks
It should be made by the end of April.
BRATISLAVA. Constipation at Púchovská Street in Rača, Bratislava, will last for a while. The Bratislava Water Company considers water pipes on the site. The repair of Račianska Street slowed down for months.
« These days, work is underway in the section of the Púchovská stop and the intersection of the Vinohrady Street by overpressure of the water supply pipe under the tram line, » said the company spokesman Matúš Stračiak.
The unexpected event, damage to the pipeline occurred in February. In the second half of March, the water company then laid part of the water pipe under the tram line using micro -tunneling. Communication has not passed a comprehensive repair of approximately 40 years.
The repair will last until the end of April. The dug Púchovska must be circumvented after Detvianska and Rustausteli, and the traffic boards also inform.
During the morning and afternoon peaks, the dug section in the Rača district of Rača forms congestion at the entrance to the city where they were not common. Local MP Miloš Máťuš, who lives in the locality, says that at these times he cannot join the road in Detvianska.
Other works are also scheduled for the section. The Slovak gas industry in the section repairs the pipeline on the streets near Vinohrady and the Carpathian Square, the Bratislava Transport Company is repaired by a tram crossing on the dug section.
« The preliminary plan is to complete work on Púchovská Street by the end of April so that the supplier can make the final finishes of the road and thus make Púchovská street in full profile, which will significantly relieve traffic in the locality, » says Stračiak from BVS.
The capital began repairing Púchov last year. The municipality allocated EUR 1.46 million to it. The project is part of the modernization of Račianska, which cost more than five million euros.
It is one of the most expensive transport projects of the city. The city paid it from part of the loan of EUR 16.6 million.
The water company replaces the pipeline on an unrequited section.