After a long time again by train? Dates were shifting but work on the electrification of the track already

After a long time again by train? Dates were shifting but work on the electrification of the track already


A possible date is the tenth March.

Humenné, Strážske. Work at railway stations in Strážský and Humenné are finished. The section of the railway line between the two cities will be handed over to early use. Trains should return to the rails on the tracks to Stakcin and Medzilaborce.

The article continues under video advertising

The article continues under video advertising

Although the Railways of the Slovak Republic did not state the specific date of the launch of the trains, as a likely possible date is featured on March 10.

The term was translated several times

The electrification of the railway line in the section Humenné – Bánovce nad Ondavou forced the traveling public to Zemplin to move from 25 September 2023 from trains to replacement buses.

Related article Follow colors, listen to coordinators' instructions. A large annual lockout on the rail has begun Read

The date of the restoration of the train operation from Humenné on both regional lines and to Strážský has moved several times from the originally planned 15 October.

At the end of the last week and earlier this week, control days were held in Brekov and stations in Strážský and Humenné.



Related article The promotion from buses to trains is not yet happening. The building has a slip half of the month Read

“On the last day of the inspection day, the client was submitted to the updated schedule of activities that need to be completed in order to start taking the track in the section Strážske – Humenné. The aim of the Railways of the Slovak Republic is to operate this section as soon as possible, ”said their spokeswoman Petra Lániková.

She stated that the building part will be completed by the end of February. « In connection with this process, on Tuesday, February 25, the procedure for early use of the track construction was initiated, » she said.



Related article Again, postponement, trains will not reach Upper Zemplin soon. Passengers are tired of annual lockout Read

The work is finishing

Currently, work in the railway stations Strážske and Humenné are finished. They are mainly focused on platforms, their roofing, access trails and underpasses, and at the Humenne Station they are currently assembling the second of two lifts.



Related article Work at the station has a slip, another date has fallen. Passengers are pushing in crowded buses Read

The work is also carried out on the installation and testing of the security device. “Technical inspections of the security facility are in the final phase. After their successful completion and tests, this part of the construction, after obtaining the license of the Transport Authority, will be put into early use, ”added Lániková.

Still in the section Strážske – Humenné and Strážske – Bánovce nad Ondavou, work continues on the reconstruction of bridges, culverts, platforms, railway bottom and upper.

A passenger underpass is built at the railway station in Michalovce.



Related article They want to drive trains in Humenné from Michalovce. Calf looked at the repair of the track, hold on, say Read

The term did not give

The completion of the complete reconstruction and electrification of the Humenné – Bánovce section is scheduled for 30 July this year.

Laniková confirmed that the train transport in the Nižný Hrabovec – Strážske – Humenné and the direction of Stakčín and Medzilaborce can be launched earlier.

« And if all the technical inspections and examinations of the security facility are successful and the procedure for early use of the runway will be successfully completed, » she added.

However, it did not give the term. The tenth March, as a possible date for the restoration of passengers and goods, was published by the City of Humenné after a check -up day on its website.



Related article The national carrier violated the law in securing replacement buses, the Office found Read

Require the repair of roads and local roads

The Mayor of Strážský Patrik Magdoško (independent) agreed at the joint meeting at the end of the week with the handover of the construction for temporary use. He demanded repair of the road from Brekov to Strážský to the roundabout and repair of the local road.

Together with the mayors of the surrounding villages, they asked for the repair of first -class roads towards Vranov, Humenné and Michalovce and the village Zbudza.

« Together we initiated a comment addressed to the Railways of the Slovak Republic and the Ministry of Transport, in which we also require the reconstruction of the third -class road in the villages of Nacina Ves and Pusté Čemerné, » he informed.

It considers electrification to be beneficial. “All replacement buses, a number of trucks, passed the roads in the city. At Strážské station was central warehouseall the material was concentrated here, the waste was exported. 50 trucks with clay left from here. The roads got a work, ”Magdoško added.